For a custom stand at a major Dubai show, start the brief about twelve weeks before opening day. That is enough time to design without rushing, clear the organiser's approvals and build the stand properly in a workshop before it ever reaches the hall.
Count back from build-up, not opening day
The date that matters is not the day the doors open but the day your build-up slot starts, usually two to four days earlier. Everything has to be designed, approved, built, test-fitted and loaded before then. Work back from that slot and the calendar fills up faster than most exhibitors expect.
What twelve weeks buys you
- Weeks 1-2Brief, concept and 3D. We turn your objectives, floor plan and budget into design options and refine one with you until it is signed off.
- Weeks 3-5Technical drawings and approvals. Structural, electrical and graphic drawings go to the organiser and venue, and we answer their comments.
- Weeks 6-10Fabrication. The stand is built and test-fitted in our UAE workshop, graphics are printed and AV is tested.
- Weeks 11-12Logistics and build-up. The stand is packed, delivered and installed by our crew, ready for your team to walk in.
If the show is in a city outside the UAE, add two to three weeks for freight and customs. For a double-deck stand, add two weeks for the extra structural approvals.
When you have less time
Six to eight weeks is workable for an inline or corner stand with a straightforward design. What gets squeezed is the design stage: fewer rounds of changes, decisions made in days rather than weeks, and materials chosen from what is in stock rather than ordered in. Under six weeks, a modular or system stand dressed with custom graphics is usually the safer route.
Organiser deadlines to watch
- Stand design submission: often four to six weeks before build-up. Late submissions can mean fines or a refused build.
- Rigging orders: anything hung from the hall ceiling, such as a banner or lighting truss, is booked through the venue and closes early.
- Power and services: electrical connections, water and internet are ordered from the venue with their own cut-off dates and late fees.
- Badges and vehicle passes: the build crew needs contractor badges, which the organiser issues only after the design is approved.
What to have ready for the first call
Your booth size and position on the floor plan, the stand type the space allows, what the stand has to do for you, and a rough budget range. A floor plan from the organiser helps, but we can start without one.